The Eureacoop cooperative has just ordered from the I.C.C. project management office, a new 11,000t sheet pile silo on a flat bottom with ventilated return. The assembly of this silo began at the beginning of July 2018 in Savigneux (Loire). It will consist of 14 cells of 20 m height, a 30 m working tower, 3 bushels of loading and 2 receiving pits. Calculation, manufacture and assembly of the silo were entrusted to the company Silos Camail who also ensured the sizing and supply of the ventilation drain. The handling and the dust collection system are provided by the company Stolz, and the civil engineering package, by Eiffage Construction. Commissioning is scheduled for December 2018.